| Rehabilitation and Construction of Kapias- Timbilil-Kamotos Road |
Public Works, Roads and Transport |
Completed
|
7,457,528.00 |
Kunyak |
Feedback |
| Chesonoi Water Project |
Water, Environment, Energy and Natural Resources |
Completed
|
2,277,400.00 |
Kunyak |
Feedback |
| Routine Maintenance of Kap Onyango-Kapkwen Road |
Public Works, Roads and Transport |
Completed
|
3,423,800.00 |
Kunyak |
Feedback |
| Tendwet water Project |
Water, Environment, Energy and Natural Resources |
Completed
|
4,536,000.00 |
Kunyak |
Feedback |
| Routine Maintenance of Sachangwan- Mariwa Road |
Public Works, Roads and Transport |
Completed
|
3,211,800.00 |
Kunyak |
Feedback |
| Timbilil Water Project |
Water, Environment, Energy and Natural Resources |
Completed
|
1,441,600.00 |
Kunyak |
Feedback |
| Timbilil Phase II |
Water, Environment, Energy and Natural Resources |
Completed
|
3,010,400.00 |
Kunyak |
Feedback |
| Chepngosos Borehole Water Project |
Water, Environment, Energy and Natural Resources |
Completed
|
902,195.00 |
Kunyak |
Feedback |
| Kichawir Water Project |
Water, Environment, Energy and Natural Resources |
Completed
|
1,533,200.00 |
Kunyak |
Feedback |
| Manyatta Water Project |
Water, Environment, Energy and Natural Resources |
Completed
|
6,013,800.00 |
Kunyak |
Feedback |
| Construction of Minihaha Box Culvert |
Public Works, Roads and Transport |
Completed
|
743,900.00 |
Kunyak |
Feedback |
| Barsiele Centre – Kipchorian – Machilil Road |
Public Works, Roads and Transport |
Completed
|
3,493,844.00 |
Kunyak |
Feedback |
| Off Main Road - Chemagel Road; Siret Centre Coffee Factory Road; Kimologit Road |
Public Works, Roads and Transport |
Completed
|
3,763,520.00 |
Kunyak |
Feedback |
| Kiptenden Kapkurin Road; Kapkurin-Kamiron Road |
Public Works, Roads and Transport |
Completed
|
6,561,740.00 |
Kunyak |
Feedback |
| Nyanza- Girimori - Kapkwen Road |
Public Works, Roads and Transport |
Completed
|
6,071,160.00 |
Kunyak |
Feedback |
| Kapkwen - Chesonoi - Kabirong - Kapkurin - Kiptenden Road |
Public Works, Roads and Transport |
Completed
|
1,086,463.00 |
Kunyak |
Feedback |
| Minihaha - Sirgoi Pry Sch Road |
Public Works, Roads and Transport |
Completed
|
2,438,585.00 |
Kunyak |
Feedback |
| Dip - Kolonget - Ngebebo Road |
Public Works, Roads and Transport |
Completed
|
6,210,708.00 |
Kunyak |
Feedback |
| Kotetni - Chemunyala - Cherara Road 4.5km; Chepsii - Kapsale Pry - Chemunyala Road 3.2km; Chelalo - Kilengel Road 3.1km; Timbilil - Ngola Road 2km; Kabirong - Kapkwen Road 3.5km |
Public Works, Roads and Transport |
Completed
|
2,630,143.00 |
Kunyak |
Feedback |